A mechanics lien is a claim against your property by someone who improved it and wasn't paid. California's constitution guarantees the right (Article XIV, §3), and the procedure is in the Civil Code starting at §8000. The rule that surprises homeowners: the claimant doesn't have to be someone you hired. If your contractor takes your money and doesn't pay the lumber yard, the lumber yard may be able to lien your home.
California makes your contractor warn you about this in writing. Every home improvement contract must carry a Mechanics Lien Warning that says, in part: "Even if you pay your contractor in full, unpaid subcontractors, suppliers, and laborers who helped to improve your property may record mechanics liens and sue you in court to foreclose the lien" (B&P Code §7159(e)(4)).
The preliminary notice
Before recording a lien, a claimant generally must give a preliminary notice to the owner, the direct contractor and any construction lender (Civil Code §8200). The rules:
- The notice is due no later than 20 days after the claimant first furnishes work (§8204(a)).
- A late notice is still allowed, but the claimant can lien only for work furnished within 20 days before the notice and afterward.
- Laborers don't send one, and a contractor with a direct contract with you sends one only to a construction lender (§8200(e)).
The contract warning puts it plainly: "BE CAREFUL. The Preliminary Notice can be sent up to 20 days after the subcontractor starts work or the supplier provides material. This can be a big problem if you pay your contractor before you have received the Preliminary Notices" (§7159(e)(4)). A preliminary notice is not a lien. It tells you who could lien your home if they aren't paid.
When the job is "complete"
Lien deadlines run from completion. Under Civil Code §8180, completion happens at the first of:
- Actual completion of the work
- Occupation or use by the owner plus cessation of labor
- Cessation of labor for 60 continuous days
- Recording a notice of cessation after labor has stopped for 30 continuous days
You can shorten the lien deadlines by recording a notice of completion with the county recorder on or within 15 days after completion. It must be signed and verified by the owner (§8182). An owner who records one must usually send copies to the direct contractor and to everyone who sent a preliminary notice within 10 days, but that duty does not apply to an owner who lives in the home as a personal residence with four or fewer units (§8190).
Recording and enforcement deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice from a sub or supplier | Within 20 days after first furnishing work | Civ. Code §8204 |
| Owner records notice of completion | On or within 15 days after completion | §8182 |
| Direct contractor records claim of lien | After finishing its contract, and before the earlier of 90 days after completion or 60 days after a recorded notice of completion or cessation | §8412 |
| Sub, supplier or laborer records claim of lien | After ceasing work, and before the earlier of 90 days after completion or 30 days after a recorded notice | §8414 |
| Lawsuit to enforce the lien | Within 90 days after recording, or the lien expires | §8460 |
A claim of lien must include a proof of service affidavit showing it was served on the owner, and a "NOTICE OF MECHANICS LIEN" in bold type (§8416).
Lien releases: conditional and unconditional
California sets four release forms by statute. A release that isn't in substantially the statutory form is unenforceable.
| Form | When it's used | Statute |
|---|---|---|
| Conditional Waiver and Release on Progress Payment | Before a progress payment is received | §8132 |
| Unconditional Waiver and Release on Progress Payment | After the progress payment has been received | §8134 |
| Conditional Waiver and Release on Final Payment | Before the final payment is received | §8136 |
| Unconditional Waiver and Release on Final Payment | After the final payment has been received | §8138 |
The difference matters. A conditional release says it "is effective only on the claimant's receipt of payment." The unconditional form warns the signer that it is "enforceable against you if you sign it, even if you have not been paid." When you pay, a conditional release from that claimant is what you want in hand. After the check clears, ask for the unconditional one.
Your contractor owes you releases too. After each payment, and before the next, the contractor must, if you ask, obtain and give you a full and unconditional release from any potential lien claimant for the work you've paid for, and you may withhold further payments until you get them (B&P Code §7159.5(a)(6)). The CSLB posts the forms on its Mechanics Lien page.
Protecting yourself during the job
The statutory Mechanics Lien Warning recommends (§7159(e)(4)):
- Get a list from your contractor of every subcontractor and supplier on the project
- Find out when each started work or delivered materials, then wait 20 days and watch for preliminary notices
- Pay with joint checks made out to the contractor and the sub or supplier who sent you a notice
Add two more habits:
- Keep payments behind the work. California bars a contractor from taking payment ahead of work performed or materials delivered, apart from the down payment (§7159.5(a)(5)).
- Since 2026 you can ask for the subcontractor list with license numbers (§7159(c)(7)).
If a lien is recorded
- Check the dates. Was a preliminary notice sent? Was the lien recorded within the §8412 or §8414 window? Note the date 90 days after recording.
- Wait out the 90 days, if that fits your case. If no enforcement suit is filed in time, the lien expires, and you can petition the court for a release order (§8480).
- Bond around it. If you dispute the lien, you can record a lien release bond for 125 percent of the claim, which releases the property (§8424).
- File a CSLB complaint if your contractor's failure to pay caused the lien. See the complaint guide.
- Talk to a lawyer before paying a claim twice or selling the property.
Related pages
Sources
- California Civil Code §§8132, 8134, 8136, 8138, 8180, 8182, 8190, 8200, 8204, 8412, 8414, 8416, 8424, 8460, 8480
- California Business and Professions Code §§7159, 7159.5
- CSLB 2026 License Law and Reference Book (PDF): California Constitution Art. XIV §3, as quoted in the mechanics lien chapter
- CSLB: Understanding Mechanics Liens
Frequently Asked Questions
Can a subcontractor put a lien on my house if I paid my contractor in California?
Yes. The Mechanics Lien Warning required in California home improvement contracts says that even if you pay your contractor in full, unpaid subcontractors, suppliers and laborers may record mechanics liens and sue to foreclose (B&P Code §7159(e)(4)). That's why the warning suggests joint checks and waiting out the 20-day preliminary notice period.
How long does a contractor have to file a mechanics lien in California?
A direct contractor must record its claim of lien after completing its contract and before the earlier of 90 days after the project's completion or 60 days after the owner records a notice of completion or cessation (Civil Code §8412). Other claimants have 90 days after completion or 30 days after a recorded notice (§8414).
What is the difference between a conditional and unconditional lien release?
A conditional release takes effect only when the claimant actually receives the payment described in it. An unconditional release is effective when signed, even if the claimant hasn't been paid. California sets the forms by statute in Civil Code §§8132 to 8138, and a release that doesn't substantially follow them is unenforceable.
How long does a mechanics lien last in California?
The claimant must file a lawsuit to enforce the lien within 90 days after recording it, or the lien expires and is unenforceable, unless you and the claimant record an agreed extension of credit (Civil Code §8460). If no suit is filed, you can petition the court to release your property (§8480).